2018–2023 BUILDING PLAN Progress


On November 6, 2018, Lexington County School District One voters, with more than 56% of the vote, voted for and passed a $365 million five-year building plan (2018–2023) that ensures that we can continue to offer our students the facilities they need now and in the future. 

This building plan includes updated safety and security systems at all district schools and facilities; three new schools to replace old schools and increase student capacity; two new elementary schools needed to accommodate student growth; renovations, additions and/or upgrades to 14 elementary schools, five middle schools, five high schools, the district's maintenance facility, technology center and community learning center; a new district transportation facility; and information technology equipment and furniture for Future Ready Classrooms at all schools.

Since the district understands that those same voters want to keep up with the progress of the building plan, we developed this webpage to do just that. This site enables voters to see what is currently happening at their child’s school and includes “before” photographs, the current phase taking place, photographs of that progress, etc. In fact, voters can click on the initials of their child’s school below and go directly to that school’s progress update.

What people are talking about...
Centerville Elementary School
Lexington Middle School
New Pelion Middle School

What’s happening now?


 

02-24-2020

 

Lexington District One pursues land for new district Transportation Facility.
Read more here.

 

12-17-2019

 

Lexington District One Board approves the purchase of White Knoll property.
Read more here.

 

09-17-2019

 

Lexington One receives final approval to purchase LMS relocation site.
Read more here.

 

07-16-2019

 

Lexington District One Board approves purchase of White Knoll property.
Read more here.

Click here for all news articles.
Click here for Architectural Selection Committee Meeting Minutes.

FAQs

Want to know how the projects impact your child’s school and community?


What’s happening at my location?

CSES, CSMS, CES, DES, FPES, GHS, GMS, GPS, LMES, LES, LHS, LTC, MGES, MGMS, MES, LMS, NPES, OGES, PES, PHS, PHES, PHMS, RBES, RBHS, RCES, SGES, WKES, WKHS, WKMS


New elementary school #18 in River Bluff attendance area
New elementary school #19 in White Knoll attendance area
New Lexington Middle School
New Pelion Middle School
New transportation facility
Maintenance facility
Rosenwald Community Learning Center
314 Main St. Gilbert
758 Magnolia St. Pelion
702 N. Lake Dr. Lexington

Carolina Springs Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Bus canopy/sitework improvements
January 2019–design phase
August 2019
Future ready classrooms
Summer 2019–design phase
New storage/equipment building
January 2019–design phase
Replace folding partition and flooring in multi–purpose room
January 2019–design phase
August 2019
Secure entry upgrades
January 2019–design phase
Upgrade interior finish
January 2019–design phase
August 2019
Water heater replacement
January 2019–design phase
August 2019
Carolina Springs Middle School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Additional bus drop canopy
April 2020–design phase
Classroom addition
April 2020–design phase
Future ready classrooms
Summer 2020–design phase
Lane widening
April 2020–design phase
New fire alarm system and cafeteria lighting
April 2020–design phase
New storage/equipment building
April 2020–design phase
Secure entry upgrades
April 2020–design phase
Centerville Elementary School

Progress:
Administration recommends new Gilbert school name.
Groundbreaking for new Gilbert school held April 30, 2019.
New Gilbert school named Centerville Elementary. Lexington District One begins Gilbert zoning process.

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Groundbreaking
May 2019
Land clearing
May 2019
Building
July 2019
Future ready classrooms
Summer 2019–design phase
Opening year
2020–2021
Deerfield Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Future ready classrooms
Summer 2019–design phase
Secure entry upgrades
January 2019–design phase
Forts Pond Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add exterior lighting in front parking area
Sept. 2020–design phase
Classroom addition
Sept. 2020–design phase
Future ready classrooms
Summer 2019–design phase
New storage/equipment building
Sept. 2020–design phase
Replace folding partition and flooring in multi–purpose room
Sept. 2020–design phase
Secure entry upgrades
Sept. 2020–design phase
Gilbert High School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add exterior hardscapes
February 2019–design phase
Fire alarm system replacement
February 2019–design phase
Future ready classrooms
Summer 2020–design phase
Interior & Exterior finish upgrade
February 2019–design phase
Program–based additions needed; Performing Arts Center, weight, wrestling
February 2019–design phase
Secure entry upgrades
February 2019–design phase
Upgrade interior/exterior lighting
February 2019–design phase
Gilbert Middle School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Additional visitor parking
June 2020–design phase
Canopy needed at front entrance
June 2020–design phase
Classroom addition
June 2020–design phase
Exterior security lighting upgrades
June 2020–design phase
Fire alarm system replacement
June 2020–design phase
Future ready classrooms
Summer 2020–design phase
Interior finish upgrades
June 2020–design phase
New dishwasher, cooler, freezer
June 2020–design phase
Gilbert Primary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add exterior canopies, walking track and hardscapes
Dec. 2018–design phase
Addition to existing storage/ equipment building
Dec. 2018–design phase
Car/bus circulation updated
Dec. 2018–design phase
Future ready classrooms
Summer 2019–design phase
HVAC controls improvement, water heater, exhaust hood
Dec. 2018–design phase
Replace wood doors and add ADA compliant door hardware
Dec. 2018–design phase
Secure entry upgrades
Dec. 2018–design phase
Student restrooms renovation, ADA upgrades
Dec. 2018–design phase
Upgrade interior finish
Dec. 2018–design phase
Upgrade interior/exterior lighting
Dec. 2018–design phase
Lake Murray Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
ADA upgrades to restrooms
Sept. 2020–design phase
Future ready classrooms
Summer 2019–design phase
February 2020
Roof replacement
Sept. 2020–design phase
Storage/equipment building
Sept. 2020–design phase
Upgrade cafeteria and stage lighting
Upgrade exterior lighting, terraced wall, and hardscaping
Sept. 2020–design phase
Upgrade interior finish
Sept. 2020–design phase
Lexington Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Demolish and remove old buildings
May 2021–design phase
Future ready classrooms
Summer 2019–design phase
July 2019
New drop off/pick–up lanes
May 2021–design phase
Replace casework
May 2021–design phase
Replace wood doors and add ADA compliant door hardware
May 2021–design phase
Secure entry upgrades
May 2021–design phase
Storage/equipment building
May 2021–design phase
Upgrade exterior lighting
May 2021–design phase
Upgrade interior finish
May 2021–design phase
Lexington High School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Replace classroom carpet
Nov. 2018–design phase
Future ready classrooms
Summer 2020–design phase
New asphalt overlay
Nov. 2018–design phase
New athletic storage buildings (2)
Nov. 2018–design phase
Roof replacement
Nov. 2018–design phase
Secure entry upgrades
Nov. 2018–design phase
Upgrade interior finish and new signage
Nov. 2018–design phase
Lexington Technology Center

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
ADA restroom upgrades
February 2019–design phase
Add canopies at welding labs and overlay asphalt at front
February 2019–design phase
Exterior painting
February 2019–design phase
Future ready classrooms
Summer 2020–design phase
Renovate locker rooms
February 2019–design phase
Replace carpet in administration and cosmetology areas
February 2019–design phase
Replace old windows
February 2019–design phase
Replace roll–up doors
February 2019–design phase
Secure entry upgrades
February 2019–design phase
Meadow Glen Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add storage/equipment building
June 2022–design phase
Future ready classrooms
Summer 2019–design phase
Secure entry upgrades
June 2022–design phase
Meadow Glen Middle School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add storage/equipment building
June 2022–design phase
Future ready classrooms
Summer 2020–design phase
Secure entry upgrades
June 2022–design phase
Midway Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add storage/equipment building
June 2022–design phase
Future ready classrooms
Summer 2019–design phase
January 2020
Replace fire alarm system
June 2022–design phase
Upgrade interior finish
June 2022–design phase
Upgrade Interior/exterior lighting
June 2022–design phase
New Lexington Middle School

Relocation progress:
The Board of Trustees accepted the administration’s recommendation to enter into option agreements.
Lexington District One amends option agreement for Lexington Middle relocation.
Lexington District One receives final approval to purchase Lexington Middle School relocation site.

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Groundbreaking
TBA
Land Clearing
TBA
Opening year
2021–2022
New Providence Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add storage/equipment building
Nov. 2022–design phase
Future ready classrooms
Summer 2019–design phase
Repaint Corridors, Replace Folding Partition
Nov. 2022–design phase
Secure entry upgrades
Nov. 2022–design phase
Update lighting controls
Nov. 2022–design phase
North Lake Dr. Lexington

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Selective demolition and repurposing existing site
Nov. 2020–design phase
Oak Grove Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add storage/equipment building
May 2019–design phase
Classroom/Fine Arts addition
May 2019–design phase
Future ready classrooms
Summer 2019–design phase
July 2019
New exterior security lighting
May 2019–design phase
New fire sprinkler system
May 2019–design phase
Replace fire alarm
May 2019–design phase
Secure entry upgrades
May 2019–design phase
Sitework Improvements
May 2019–design phase
Update student restrooms
May 2019–design phase
Pelion Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add storage/equipment building
July 2019–design phase
Future ready classrooms
Summer 2019–design phase
October 2019
Replace carpet in chorus room
July 2019–design phase
Replace ceiling tiles and interior lighting
July 2019–design phase
Replace roof on latest addition
July 2019–design phase
Replace serving lines in kitchen
July 2019–design phase
Pelion High School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add school store in commons area
Dec. 2018–design phase
Add stadium visitor locker room
Dec. 2018–design phase
Future ready classrooms
Summer 2020–design phase
New track locker room, concessions and restroom
Dec. 2018–design phase
New weight/wrestling room
Dec. 2018–design phase
Secure entry upgrades
Dec. 2018–design phase
Track modifications
Dec. 2018–design phase
Upgrade audio/lighting in auditorium
Dec. 2018–design phase
Upgrade lighting in gym
Dec. 2018–design phase
Pleasant Hill Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add kitchen loading dock
August 2022–design phase
Add storage/equipment building
August 2022–design phase
Future ready classrooms
Summer 2019–design phase
Replace carpet in admin/ foyer with hard tile
August 2022–design phase
Replace carpet with sports flooring in the multi–purpose room
August 2022–design phase
Replace folding partition
August 2022–design phase
Secure entry upgrades
August 2022–design phase
Pleasant Hill Middle School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add canopies and sidewalk
Nov. 2022–design phase
Future ready classrooms
Summer 2020–design phase
Replace cafeteria lights
Nov. 2022–design phase
Secure entry upgrades
Nov. 2022–design phase
Red Bank Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add storage/equipment building
July 2019–design phase
Future ready classrooms
Summer 2019–design phase
July 2019
Replace food service equipment
July 2019–design phase
Replace wood doors and add ADA compliant door hardware
July 2019–design phase
Secure entry upgrades
July 2019–design phase
Upgrade student restrooms and interior finishes
July 2019–design phase
River Bluff High School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Future ready classrooms
Summer 2020–design phase
Secure entry upgrades
January 2022–design phase
Upgrade parking lot landscaping
January 2022–design phase
Upgrade student canopy
January 2022–design phase
Rocky Creek Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Future ready classrooms
Summer 2019–design phase
Secure entry upgrades
January 2019–design phase
Rosenwald Community Learning Center

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Ceiling upgrades
October 2020–design phase
Future ready classrooms
October 2020–design phase
Secure entry
October 2020–design phase
Walk–in cooler and serving line replacement
October 2020–design phase
Saxe Gotha Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add storage/equipment building
August 2021–design phase
Future ready classrooms
Summer 2019–design phase
Septermber 2019
Replace exterior windows
August 2021–design phase
Replace food service equipment
August 2021–design phase
Secure entry upgrades
August 2021–design phase
Upgrade student restrooms and Interior finishes
August 2021–design phase
White Knoll Elementary School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add lane at bus drive
April 2019–design phase
Add storage/equipment building
April 2019–design phase
Future ready classrooms
Summer 2019–design phase
October 2019
Kindergarten addition
April 2019–design phase
Replace fire alarm system
April 2019–design phase
Replace kitchen exhaust hood
April 2019–design phase
Secure entry upgrades
April 2019–design phase
Upgrade exterior windows
April 2019–design phase
White Knoll High School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Interior Finish Upgrades
January 2019–design phase
Classroom addition
January 2019–design phase
Future ready classrooms
Summer 2020–design phase
Performing arts center
January 2019–design phase
Replace ceiling tiles in gym and cafeteria
January 2019–design phase
Replace partial roof and HVAC
January 2019–design phase
Re-purpose of existing auditorium
January 2019–design phase
Secure entry upgrades
January 2019–design phase
Water heater replacement
January 2019–design phase
White Knoll Middle School

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Add canopy at bus pick-up/drop off
July 2019–design phase
Add storage/equipment building
July 2019–design phase
Future ready classrooms
Summer 2020–design phase
Replace ceiling tiles, interior lighting, carpet and toilet partitions
July 2019–design phase
Replace exit lights and add exterior lighting
July 2019–design phase
Update student restrooms
July 2019–design phase


314 Main St. Gilbert

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Selective demolition and repurposing
Dec. 2019–design phase
702 North Lake Dr. Lexington

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Selective demolition and repurposing existing site
Nov. 2020–design phase
758 Magnolia St. Pelion

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Selective demolition and re-purpose of existing site
April 2020–design phase
Maintenance Facility

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Partial roof replacement
March 2019–design phase
New Pelion Middle School

Progress: Groundbreaking for new Pelion school held April 30, 2019.

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Replace and relocate
May 2019
May 2019
Building
July 2019
Clearing
May 2019
July 2019
Future ready classrooms
Summer 2020–design phase
Groundbreaking
May 2019
May 2019
Opening year
2021–2022
New River Bluff Area Elementary School

This project has been delayed as the district continues to seek a site for the project.

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Future ready classrooms
Summer 2019–design phase
New facility, secured entry
June 2019–design phase
Opening year
2022–2023
New Transportation Facility

Progress:

• Lexington District One pursues land for new district Transportation Facility

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
New facility
Sept. 2019–design phase
New White Knoll Area Elementary School #19

Progress:
Lexington District One enters into option agreement
Lexington District One Board approves purchase of White Knoll property
• Lexington District One Board accepts the administration’s recommendation to purchase property

Before Photo
Project
Anticipated Start Date
Current Photo
Completed Date
Future ready classrooms
August 2021–design phase
New facility, secured entry
August 2021–design phase
Opening year
2023–2024